Sunday, March 16, 2008

Tiling the Shower

Day 1



















Day 2


C is a trooper, but I think this may be too tedious for him!

Meanwhile, I finished priming the hallway. I have only 2 coats of paint, and cutting of trim to return it to the state it was in only 5 days ago. I know I really wanted to have the walls skim coated but now I don't know what I was thinking!!

Sunday, March 9, 2008

Gardening, Beth's Tree & Sheetrock Prep

C & I spent much of the weekend enjoying the outdoors, granted it was by working on our yard. We made a trip out to Recycled Gardens on Saturday where we bought two mature plants (one Laurel and one Camillia) for a steal of a deal. We also made visited Portland Nursery, where we found exactly what we were looking for, and spent the money we save by getting used plants earlier in the day. While we were out, a dump truck delivered bark mulch.


The new plants are in the ground, and a third of the mulch is spread. We also did some repair work to the lawn where the plumbers had ripped it up during the install of the sewer line.




Perhaps the most meaningful yard project was the planting of a Dogwood in memory of my Mom. When my Mom was growning up in Virginia, her father planted three Dogwoods, one for his wife and for each of his two daughters. When C & I desgined the front yard we included a Dogwood as a center piece, when was planted the week of our wedding ... a ceremony of sorts. Upon my Mom's passing, her sister suggested that we add a second Dogwood to our yard. Today was the day we made it happen. Complete with the use of some of her ashes, Beth's tree has been planted. It sits outside of our front windows, framing the view.

Finally, we prepped the new bathroom & utility room space for the sheetrock to be installed tomorrow. In addition to finishing those rooms, we will also skim coat the main hallway to repair bad seaming and patch the wholes from the installation of the attic stairs. I'm so excited to come home tomorrow and see the progress!

Sunday, February 24, 2008

Mystery Date




Last month, C sent me an invitation to join him on a "Mystery Date." I knew nothing but the day on which it would occur. Yesterday was the day I'd been waiting for.

After a nice breakfast, C told me that we would need to clean our guest room as we had a dog sitter coming and that I should pack an overnight bag. The bag was the easier of the two tasks. After a couple of questions to determine formal or casual, indoor or out, I was all set. Then came the guest room.

Since September we have been piling parts and pieces for the new bathroom in there. Not to mention scraps from Chrismas, overnight bags from weekend trips, and the pile of dry cleaning I'd yet to deal with. I think the preasure of knowing someone was coming so soon was exactly what we needed to sort through all of the stuff.

House in order and bags packed we headed off. A quick stop at the cleaners and Goodwill, and then on to I-84 east bound. Skamnia Lodge? Maryhill Vineyard? My mind was wondering where we could be heading. C pulled off the road at Multnomah Falls. It was lovely, as usual. Before we could get out of the car he turned it around and headed back to town. Where were we going???

Just off I-84 in Corbett sits the View Point Inn (www.theviewpointinn.com). He had arranged for us to stay in the suite, and made dinner reservations. The view from our room was spectactular! There was an amazing sunset, glowing red, over the Columbia River. We had a roaring fire in the fireplace, sipped wine, and completely relaxed. This morning we enjoyed brunch, again taking in the view of the Gorge, before made the 15 minute drive home.

It was a fantastic suprise, and a place I'm sure we will go to again. To all my Portland friends, check this place out! Great for Mother's Day brunch, watching 4th of July fireworks, or for a surprise date with your special someone.

Monday, January 28, 2008

Tying up loose projects...

Our sheet rocker (Alternative Drywall, 503-504-8968) was out last weekend to take a look at our project. While they aren't available until March, we agree that a good contractor is worth the wait.

Rather than sit idle between now and the completion of the sheet rock I started thinking about what projects we have around the house sitting untouched. I'm realizing that my/our follow through has been somewhat lacking. Case in point, our floors. They were finished November '06, and we've yet to complete the trim. It drives us both crazy, and yet we've seemed to have lived with it this long. But, no more! We will get it done.

Then there is the ceiling in the office. It has a big spot which remains unpainted from when C moved the closet. Again, this has been sitting since Nov. '06. Twice I have taken time off of work to complete this project, yet the primer remains.

I don't usually consider myself a slacker, but I can't come up with any reason as to why I haven't completed these projects. We've got at least four weeks until we can move on to the next phase in the bathroom/utility room. I hope that in that time I can get some stuff done.

Sunday, January 20, 2008

Bring in the sheetrock!

It is official, we are ready for the sheetrock! The bathroom/utility room project looks pretty much the same. Regardless, we've hit a major milestone ... we're ready for sheetrock. This also means that our tools have been put away, and we've cleaned up the space.

I took the liberty of doing a couple of quick floorplans to give you an idea of the transformation.

Before:


After:


I'll have new pictures as soon as we have walls. Here's hoping it is soon!!

Sunday, January 13, 2008

Destractions

I've been a slack of a blogger lately. It has been nearly a month since I've posted anything dispite the best of intensions. While I've not made time to write, I have captured 35 stars in Super Mario Galaxy, each getting me one step closer to saving Princess Peach.

By way of catching you up to date:

We had a wonderful gathering of ugly sweaters


New Years included the best hat of all time!


We just spent a lovely weekend in Eugene, catching up with many friends and leaving Rocko to wear himself out on a 2-day play date.


The bathroom/utility room project is progressing. It doesn't look much different, dispite the numerous hours spent in there. The HVAC has been re-routed, the electrical is finished, and all the walls are framed. We are getting closer to calling in the sheetrockers, which is when the change will really start to show.

Sunday, December 16, 2007

Bathroom Update

After much delay and a number of discussions with the business owner, the plumbers (American Plumbing Services) finally finished up 2 weeks ago. Since then, we've took a little break to retreat to the coast and hosted a holiday sweater party (watch for the upcoming post and associated pictures). The work on the bathroom does continue, albeit at a slow pace. To say that we have run out of steam is an understatement! Regardless, progress is being made.




















The above picture shows the framing for the wall that will separate the bathroom from the utility room, the pocket door neatly stashed in it's pocket, and the white oval on the wall is the interior of the medicine cabinet. The area on the right, with the pocket door, is the shower stall, and the toilet and closet will be to the left of the vanity/medicine cabinet.


The above picture is of the shower as it currently stands. The Wonder Board is up, and awaiting tile. We picked out a great glass mini-subway tile in greens and browns for the accent tile while the majority of the shower will be a white ceramic subway tile. We have a lot of work to do before we lay any tile, but I'm trying to keep the goal in mind.